Soft soil engineeringRailway Connection between Incheon International Airport Terminal 1 and 2 |
Category |
T / K Basic & Detailed design |
Client |
Korea Rail (KR) Network Authority |
Contractor |
Hyundai Development Company |
Period |
June 18, 2012 ~ November 27, 2013 |
|
|
|
|
|
|
|
|
Project Information |
|
-
Location
Incheon International Airport Terminal 1 ~ Terminal 2, Korea
-
Description
- Total L = 5,940m
-
Tunnel L = 2,181m
-
Entrance Line L = 2,253m
-
Exit Line L = 2,220m
-
Technical Issues
- Establishment of improvement methods for clay layer (N<5, 2~13m depth) in Entrance & Exit Line section
- Design of ground improvement methods (preloading, GCP, pile slab) based on reliable settlement design calculations
|
|