- Location
Sambang-ri, Beobwon-eup, Paju-si, Gyeonggi-do ~ Deokdo-ri, Gwangjeok-myeon, Yangju-si, Gyeonggi-do, Korea
- Description
- Total L = 7,480m
- 3 Tunnels L = 5,314m
- 2 Bridges L = 328m
- Technical Issues
- Design of inclined tunnel instead of vertical shaft for improvement of constructability, construction period and rescue operation in accident.
- Design of one-way excavation plan, considering dip direction of joints for improvement of stability during excavation
- Extending the width of the road shoulder (2.5 → 3.0m) to improve driving safety and maintenance convenience
- Installing VMS (Various Message Sign) and sunlight blocking facilities for minimization of direct sunlight effects and securing driving safety
|