Location
Daegang-myeon, Danyang-gun, Chungcheongbuk-do ~ Punggi-eup, Yeongju-si, Gyeongsangbuk-do, Korea
-
Description
-
Total L = 14,645m
-
3 Tunnels L = 11,248m
-
Earthworks L = 3,184m
-
Bridge L = 213m
-
Technical Issues
- Design for the disaster prevention of a long tunnel and minimization of environmental damages on National Park
- Adaptability analysis of high efficient rapid construction equipment to obey the construction period
- Design of auxiliary reinforcement methods according to the size and position of limestone cavities
|