Description
-
Total L = 1,730m
-
Tunnel L = 1,347m
-
Station L = 330m
-
Vent-Shaft L = 53m
-
Technical Issues
-
Design of tunnels in urban area (under the existing park and sports stadium) for reduction of noise and vibration impacts to prevent the complaints from citizens
-
Application of a Shield TBM method for watertight tunnel to minimize ground settlement of cultural heritage protection area
-
Design of a Shield TBM considering mixed complex ground conditions and a sharp curved (R = 300) tunnel alignment
|